Telling a scheduled outage from a forced outage using satellite imagery

Cooling towers at a power plant releasing steam under a cloudy sky

A unit goes dark in your imagery feed. No stack plume, cooling tower steam has dropped off, coal pile hasn't moved in two passes. Before you touch your generation model or your basis position, you need to know one thing: was this scheduled, or did something break.

The utility's own NERC GADS filing will eventually tell you, coded as PO for a planned outage, MO for maintenance, or one of the forced classes (U1, U2, U3) depending on how much notice the operator had before the unit tripped. The problem is timing. GADS data lags by weeks, sometimes a full quarter, and EIA-860/923 filings aren't built for anyone trying to mark a position this week. By the time the filing clears, the market has already moved on without you.

What GADS actually codes, and what imagery can't see

GADS captures cause: a boiler tube leak, a turbine trip, a scheduled outage. Imagery works from a different layer entirely. A satellite pass gives you a thermal signature and a coal-pile reading, the physical footprint of a shutdown, with no visibility into why it happened. So the honest answer to "can imagery tell me it's a forced outage" is: not directly, not from one pass. What imagery gives you is the pattern, and pattern is most of what a GADS code is standing in for anyway.

A planned outage almost always has a shape to it. Generation tapers down over several days rather than dropping in one pass. Coal deliveries slow or stop in the weeks leading up to it, because nobody stockpiles fuel for a unit they're about to take offline for a month. The cooling tower plume fades gradually, consistent with a controlled shutdown sequence, not a trip.

A forced outage usually doesn't give you that runway. You'll see a unit at full thermal signature in one weekly pass and dark in the next, with the coal pile still sitting at a working inventory level, as if the plant expected to keep burning it, with no tapering and no drawdown beforehand. That abruptness, paired with the absence of any prior fuel-delivery slowdown, is the clearest imagery tell you'll get.

The signals that separate the two in the imagery record

Three things matter here, and they matter together, not one at a time.

Stack and cooling-water signature over consecutive weeks shows you the shape of the shutdown. A slow fade reads as planned. A hard stop reads as forced.

Coal-pile volumetrics tell you whether the operator was still planning to run. A pile that's been drawn down before the outage suggests the plant knew it was coming and stopped ordering fuel. A pile that's sitting full, or still being delivered to, right up to the week the unit went dark is a much stronger forced-outage signal than the thermal drop alone.

Duration against the season matters too. Spring and fall outages that land during traditional maintenance windows and run four to six weeks are more often planned. An outage that starts mid-summer during peak demand, when no rational operator schedules maintenance voluntarily, is already suspect before you look at anything else.

None of these three alone proves cause. A slow taper during an unusual month, or a full coal pile sitting next to a dark stack in August, is the combination that should make you treat it as forced until the filing says otherwise.

Where the cadence of the data matters

A single weekly image is a snapshot. A planned-versus-forced call is a judgment made across several of them, which is exactly why cadence matters more than resolution here. One sharp image of a cold stack tells you a unit is offline. A run of four or five weekly passes, stacked against delivery and generation data, tells you how it got that way.

That's the gap a weekly nowcast series is built to close: stack and cooling-water readings tracked alongside coal-pile levels for a named plant, run against your own generation and commodity data instead of waiting on the next EIA cycle. If you're trying to mark a forced outage before the GADS filing catches up, that's the use case Power Plant Activity was built around.